MEKA is proud to be a part of one of the most important and prestigious mining projects in Turkey. Our growing reputation for quality and reliability has resulted in an order for the supply of a Zinc-Lead ore and screening plant, which was successfully brought into operation at the end of 2021.
LİNEER METAL started the construction of a 90000 tons per year greenfield zinc smelter at Siirt. Spread over 200 acres, the facility will entail an investment of 500 million USD in phases, create more than 3000 direct and indirect jobs, and will be operational by 2022. The plant will substantially increase employment and thereby boost the economy in the region. The new facility will be a model plant - incorporating the latest technology, automation, and the highest standards of environment and health safety compliance. Zinc and lead ores are mined in key mining sites of Hakkari, Siirt, Şırnak, and smelting and refining of zinc-lead and other minor metals at processing operation at Siirt Industrial Zone.
Plant Design Criteria
• Material to be processed is Zn-Pb Ore with a solid density of 3.4 tons/m³
• Feed material size : 0-600 mm
• 1 grade of the product is produced, 0-10mm
• The hourly production of the required product is 100 metric tons/hour.
• Number of working hours: 8 hours per shift, 3 shifts per day, 360 days per year
Equipment Selection
FEED HOPPER with 18 m³ volume,
MAF 1245 APRON FEEDER
MSH 2060/3 INCLINED HEAVY DUTY SCREEN with dust encapsulation
SURGE BIN WITH VIBRATING FEEDER
WITH STANDARD COARSE CHAMBER
SURGE BIN WITH VIBRATING FEEDER
CONE WITH STANDARD MEDIUM CHAMBER
MS 2060/2 INCLINED SCREEN with dust encapsulation
PRODUCT SILO
BELT CONVEYORS
MEKA continues to be the primary choice of the mining leaders’ in the world with its high quality and reliable and screening solutions.
The Mexican aggregate production industry is evolving faster than ever. The increasing demand for roads, housing and infrastructure in the country creates a need to produce more and more raw materials at competitive prices with minimal environmental impact. The constant and consistent supply of quality aggregates is one of the industry’s prime challenges.
MoreIn our 250 t/h capacity plant, which we established in Bou Saâda, Algeria, superior performance and efficiency have been achieved.
MoreM100 and M120 mobile concrete batching plants were the cornerstones of a new residential complex in Al-Mansour, Baghdad. In this comprehensive project, our customer, who had previously completed successful projects with our K145 model, preferred MEKA's mobile solutions this time as well. This complex, consisting of 30 units 12-storey buildings in total, was designed to meet all the needs of modern life.
MoreThe construction of the one of the most prestigious marina projects in Les Almadies, Dakar, has started with MEKA concrete batching plant. The Spanish company chose MEKA for this major project, which involves the construction of a marina and a luxury hotel by the sea in Almadies.
More